2018/06/05 - Extended Downtime Deployment Discussion Thread!

UPDATES:

11:00 UTC

TRANQUILITY HAS BEEN TAKEN OFFLINE & DOWNTIME HAS BEGUN!

11:15 UTC

CHANGES THAT ARE NOT PART OF THE OUTPOST PHASE OUT ARE CURRENTLY IN PROGRESS.

11:17 UTC

THE OUTPOST PHASE OUT HAS BEGUN - 5/1217 OUTPOSTS CONVERTED.

11:32 UTC

OUTPOST PHASE OUT ONGOING - 75/1217 OUTPOSTS CONVERTED - TIME ELAPSED IS 16 MINS.

11:47 UTC

OUTPOST PHASE OUT ONGOING - 223/1217 OUTPOSTS CONVERTED - TIME ELAPSED IS 30 MINS.

11:58 UTC

ACCIDENTAL RELEASE OF A DUMP OF FEDOS FROM UNITY STATION. CLEANUP IS ONGOING.

12:02 UTC

FEDOS STILL SCUTTLING ABOUT. SEVERAL NETS HAVE BEEN DEPLOYED. NOTHING TO SEE HERE.

12:08 UTC

OUTPOST PHASE OUT ONGOING - 441/1217 OUTPOSTS CONVERTED - TIME ELAPSED IS 50 MINS.

12:23 UTC

WE’RE NOW ROUGHLY 50% OF THE WAY THROUGH THE OUTPOST CONVERSION PROCESS.

12:40 UTC

CONVERSION STILL ONGOING - TOTAL CONVERSION TIME SHOULD BE A LITTLE OVER 2 HOURS.

13:20 UTC

OUTPOST PHASE OUT ONGOING 1112/1217 OUTPOSTS CONVERTED.

13:25 UTC

OUTPOST CONVERSION COMPLETE - RUNTIME 02:08:11

13:27 UTC

CHECKS CURRENTLY ONGOING - TQ STARTING UP SOON

13:34 UTC

REGULAR DOWNTIME JOBS NOW ONGOING - TQ STARTING UP SOON

13:46 UTC

TQ IS NOW STARTING UP FOR TESTING IN VIP MODE

13:52 UTC

VIP MODE TESTING COMPLETE

13:56 UTC

TRANQUILITY IS NOW ONLINE AND ACCEPTING CONNECTIONS!

19 Likes